West Bank Path Repairs (Greenway Bridge to Stephen (Project completed)

Completed: Yes
MTIP: None Construction Year: 2012
Jurisdiction: City of Eugene Mode: Bike
Pedestrian
Description:

Sections of the West Bank Path will be reconstructed as a 12-foot-wide concrete facility, making it safer for the thousands of people who walk, run, cycle and skate on the path each year.

Timeline: Summer 2012 - Fall 2012
Traffic Impacts:

The path will be closed to through traffic at times during construction. Use the North Bank Path or River Road as alternate routes.

Work Schedule:

More detailed scheduling information will be provided once construction begins.

Funding:

The primary source of funding for the estimated $350,000 project is the 2008 voter-approved bond measure to fix streets and bike paths.

Contact: Doug Singer
Project Notes:

More information about this project is availabl

Short Description: Construction is anticipated to begin in mid-July.
 