South Bank Path Rehabilitation Project (Project completed)

Completed: Yes
MTIP: None Construction Year: 2013
Jurisdiction: City of Eugene Mode: Bike
Description:

This project will relocate a segment of shared-use path adjacent to the Willamette River in Skinners Butte Park. It will also replace numerous panels of the existing concrete path that are showing signs of deterioration.

Timeline: Fall 2013
Traffic Impacts:

Path closures, with detours on Cheshire Street.

Work Schedule:

Detailed information will be posted on this site once construction begins.

Funding:

Major source of funding for this project is the 2008 voter-approved bond measure to fix streets and shared-use paths.

Contact: Doug Singer
Project Notes: Project fact sheet
Short Description: Path Rehabilitation Project
 