OR126B: Willamette River Bridge (Springfield) Rehabilitation (Project completed)

Completed: Yes
MTIP: STIP 18386 Construction Year: 2014
Jurisdiction: Oregon Dept. of Transportation (ODOT) Mode: Road
Description:

This project repairs and replaces corroded steel on the westbound Willamette River Bridge (Main Street) in Springfield.

Business Access During Construction? Yes
Road Closure:
  • Complete overnight closures of the bridge are scheduled for:
  • Monday, March 3, 2014 at 9 PM until Tuesday, March 4, 2014 at 4 AM
  • Thursday, April 3, 2014 at 9 PM until Friday April 4, 2014 at 4 AM
  • Thursday, May 15, 2014 at 9 PM until Friday, May 16th, 2014 at 4 AM
Timeline:

February 2014 – June 2014

Traffic Impacts:

This project will affect only the westbound, historic steel bridge which in Main Street in Springfield, The eastbound bridge, which is South A Street, will not be affected.

While much of the work will be done from platforms attached beneath the bridge, pedestrians and bicyclists should expect sidewalk closures, and motorists can expect intermittent lane closures.

  • Complete overnight closures of the bridge are scheduled for:
  • Monday, March 3, 2014 at 9 PM until Tuesday, March 4, 2014 at 4 AM
  • Thursday, April 3, 2014 at 9 PM until Friday April 4, 2014 at 4 AM
  • Thursday, May 15, 2014 at 9 PM until Friday, May 16th, 2014 at 4 AM

When the bridge is closed, motorists trying to access points west of the bridge should take Pioneer Parkway (OR528) northbound, to OR126 westbound, to I-5 southbound, take Exit 189 to Franklin Blvd. (OR225) northbound, to OR126 Business/Main St.

Work Schedule:

The contractor is working various day and night shifts at this time.

Funding:

This project is funded with ODOT Maintenance funds.

Contact: Chuck Lemos
 