LCOG point2point LTD ODOT Lane County Eugene Springfield Coburg Working together to keep you moving
KeepUsMoving.info

8th Avenue, Lincoln Street, and Washington Street Paving Project (Project completed)

Completed: Yes
MTIP: N/A Construction Year: 2016
Jurisdiction: City of Eugene Mode: Road
Description:

8th Avenue will be repaved from Monroe Street to Lincoln Street. Lincoln Street will be repaved from 13th Avenue to 5th Avenue. Washington Street will be repaved from 13th Avenue to 8th Avenue.This project is primarily intended to repair the street pavement, but the full scope of the work is not yet determined and additional elements may be added as the site is further reviewed.

Business Access During Construction? Yes
Timeline:

This project is scheduled for construction in the spring of 2016.

Traffic Impacts:

Drivers should expect lane closures and lane shifts during construction.
With any construction, drivers should expect equipment and workers in the roadway leading to congestion and delays during the work.

Work Schedule:

Prior to the start of street construction, the City’s arborists may be on-site trimming trees to prevent overhead limbs from being damaged by construction equipment. Also prior to construction, utility companies (water, electricity, gas) may be on-site adjusting their facilities in order to avoid conflicts with the work and prevent damage to their facilities.

Funding:

The primary source of funding for 8th avenue comes from the City of Eugene local gas tax. The primary source of funding for Lincoln and Washington streets comes from the Street Repair Bond passed by voters in 2012.

Contact: Chuck Mueller
Short Description:

8th Avenue will be repaved from Monroe Street to Lincoln Street. Lincoln Street will be repaved from 13th Avenue to 5th Avenue. Washington Street will be repaved from 13th Avenue to 8th Avenue.

 
KeepUsMoving.info: Working together to keep you moving