LCOG point2point LTD ODOT Lane County Eugene Springfield Coburg Working together to keep you moving
KeepUsMoving.info

Crow Road (Project completed)

Completed: Yes
Jurisdiction: Lane County Mode: Road
Bike
Pedestrian
Description:

This project includes repairing failing asphalt.

 

Business Access During Construction? Yes
Timeline:

Construction is anticipated to be between June 13 and September 16, 2016.

Traffic Impacts:

The work will restrict traffic to a single lane during construction activity, controlled by flaggers. The road will be opened to traffic at the end of the work day.  Pedestrians and bikes will also be impacted.

Work Schedule:

The project work schedule has not yet been developed but will occur between June 13 and September 16.

Funding:

This project is funded by the Lane County Road Fund 

Contact: Jim Steers
Short Description:

Street repaving for Crow Road. See map for detailed information on location of street construction.

 
KeepUsMoving.info: Working together to keep you moving