LCOG point2point LTD ODOT Lane County Eugene Springfield Coburg Working together to keep you moving
KeepUsMoving.info

Regional Bicycle Counters

Completed: No
MTIP: N/A Construction Year: 2017
Jurisdiction: City of Eugene Mode: Pedestrian
Description:

• This project will construct permanent, automatic bicycle counters at ten to twelve locations in Eugene and Springfield.
• The automatic bike counters are actuated by induction loops installed in the pavement.

• Eugene: Alder St near 18th Ave, Amazon Path north of 24th Ave, Frohnmayer Bridge, Greenway Bridge North, Greenway Bridge South, Delta Ponds Bridge, 10th Ave and Adams St, Beltline Path north of Roosevelt Blvd, Alder St near Franklin Blvd.

• Springfield: EWEB path at 5th Street, Pioneer Parkway south of Q St, North Bank Path at D St.

Business Access During Construction? Yes
Traffic Impacts:

• Cyclists and pedestrians should expect a few days of disruption at each site during the path work.
• Cyclists my need to merge with motor vehicle traffic for a few days at some locations, such as Alder Street near Franklin Boulevard.

Work Schedule:

• This project is scheduled for construction in the fall of 2016.
• Prior to the start of construction, there may be electric utility work to extend power to some sites.

Funding:

• This project is primarily funded by a federal grant obtained by the Lane Council of
Governments.

Contact: Patrick Cox
Project Notes:

https://www.eugene-or.gov/roadwork

Short Description:

• The City of Eugene is designing and managing construction of this project on behalf of the Lane Council of Governments (LCOG).

 
KeepUsMoving.info: Working together to keep you moving